Skip to Content

Is Production order Quantity must be equal to requirement quantity?

Aug 01, 2017 at 01:32 PM


avatar image

Production confirmation is possible by issuing lowest qty against the require qty by BOM Qty

Production order Qty 50 (Material XXXXX)

For completing this (XXXXX) I need material (YYYYY) 100 Qty

But In SAP can be Confirm at CO11N of 50 (XXXX) by issuing 50 qty of (YYYYY) Material

can You suggest me is it possible in practically

please explain me how to restrict that.

I need required qty(as per BOM YYYYY) must be equal to Production(XXXX) order qty

Ex:Production order Material (CAR)

BOM: 4 Tyre is required to complete one CAR but is SAP 3 Tyre or 5 Tyre is is enough to complete the one CAR

All Expert Please suggest me

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Aug 01, 2017 at 03:15 PM


There is no option in standard to do that. You can use BAdIs WORKORDER_CONFIRM or WORKORDER_GOODSMVT to add your own check.



Show 5 Share
10 |10000 characters needed characters left characters exceeded

Sir please Guide me how to do the enhancement for this scenario's

Between BOM qty and Production Yield Qty


Hi Prasath

This is a very complex enhancement and it depends on your business requirements and customer specific scenarios. Unfortunately, this is not something that we can do through and SCN thread and you need to discuss with your users and development team.




My customer is using MTO & MTS

They don't wanna get accept production confirmation if material (Required BOM Qty) not available for operation.


Consult with your technical team. Give them requirement with the badi suggested by catenao.

Best regards

Shailesh Mishra


For us is too challenging to enhance this customer requirement ..

I hope you will guide us.