Dear All,
I have triggred the project through planning strategy 85 when i am making a quotation.The account assignment is done for the project.The planned cost in the network is updated in the quotation.But i am not able to get the activity cost in the
WBS element though it is available in the network level.
Is there any other setting to be done in the IMG ?
My client scenario needs a close interaction(flow) of data from PS to SD
I am trying to do DIP profile and Resource related billing.
I also understand that i may have to use planning strategy 21.Can some one kindly provide me detail study material for planning strategy 21
Rewards are assured for timely & valuable help.
Thanking you,
Best Regards,
R.Srinivasan