Hi Guru's ,

The default value for the valid to date is 31/12/9999 for the inspection plan. But the requirement is the valid from date is 01/08/2017 is entered but the valid to date is automatically assigned as 31/12/9999. I need to change the valid to date for the inspection plan with out using the Change number

Thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Aug 01, 2017 at 03:17 PM
0

Hello

You cannot change the validity date after the creation, but you can set the deletion flag for a period in the future, for example, from 1/1/2018 to 31/12/9999. This way, the plan can only be used until the end of the year.

Regards,

Caetano

Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Caetano,

Thanks for the prompt reply .

But the requirement is while creating the inspection plan the valid to date has to be changed. Inspection plan should have the valid from date as 1/1/2018 and the valid to date should be 1/1/2020 but the system by default takes the valid to date as 31/12/9999. The inspection plan is used i cannot assign the deletion flag.

Please let me know how to change the valid to date as per the requirement.

Regards,

Gouthm

0

Hello

You can set the deletion flag for a date in the future. In QP02, when you enter the transaction, set the key date 1/1/2020 and then set the deletion flag. Your plan will be active until 1/1/2020 and the deletion flag will be active from 1/1/2020 to 31/12/9999.

Regards,

Caetano

0
avatar image
Former Member Aug 04, 2017 at 07:05 PM
0

The best way is to change the inspection plan status to '1' (created) if you don't want to use it.