Skip to Content

Is it possible to calculate Interest on PM orders?

I have not found any place to assign an Interest Profile directly.

Would be the only alternative to settle to the WBS and run Interest calculation on the WBS-elements?

Thank you!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 01, 2017 at 01:04 PM

    Got from the SAP help:

    If you want to include the values from assigned orders and networks in the interest calculation, you must first settle these objects to the WBS element and then execute an interest run.

    Add comment