Partial Planned Order Creation possible or not??

If a production order is partially confirmed and then TECO the order. Is it possible for this order to create new planned order in MD04 screen by re run the MRP run for the rest of order quantity??

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 28, 2017 at 05:06 PM

    Hello

    If there is an open requirement that was not fulfilled by this production order, then the next MRP run will create a planned order to cover the remaining requirement quantity.

    Regards,

    Caetano