Partial Planned Order Creation possible or not??

Jul 28, 2017 at 03:43 PM

59

avatar image
Former Member

If a production order is partially confirmed and then TECO the order. Is it possible for this order to create new planned order in MD04 screen by re run the MRP run for the rest of order quantity??

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Jul 28, 2017 at 05:06 PM
0

Hello

If there is an open requirement that was not fulfilled by this production order, then the next MRP run will create a planned order to cover the remaining requirement quantity.

Regards,

Caetano