Dear Expert,

We are planning to use capacity levelling (CM25) for the finite scheduling of production order. We have requirement only to schedule production order.

Now during the capacity levelling (CM25) we want to display only production order and not planned order, but standard SAP shows both in the CM25 for all profile. How we can display only production order in CM25? Is there any way we can restrict planned order?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Jaydeep Pipalia Jul 28, 2017 at 12:43 PM

Dear All,

This issue is resolved, we have option of filter in CM25 for profile: SAPSFCG004. In this enter the production order, select filter and select 1 in order category for work order detailed scheduling.

w7cs5.png (9.5 kB)