Hi Experts,

My question is: in a project, i need a product (called X) which is manufactured in our plant. X has got a BOM, so in my internal activity, i call X and its BOM.

This product has a Routing, just an assembly operation of the differents components.

In the project, we don't see the routings (with the work center, type of activity (labour and machine)) (in my PS work center i can't have 2 activity type.)

moreover, for my schedule, i'd like to obtain the time it needs to product X in the activity by the routing.

do you have some solutions

Thanks for help