on 07-24-2007 7:33 AM
Hello Friends,
what logic system applies for Retest date calculation? which date it considers to add to Inspection Interval ? Does it apply the same logic to calculate Retest date during second time of test i.e. Inspection lot is created due to recurring inspection.
Regards
mahesh
Hi Mahesh,
System calculate the Retest Date on the basis of GR Date.
Eg. if you gave the inspection Interval as 30 days & the GR is prepared on 1st day of month then the next recurring inspection lot creates on 1st day of next month if the stock is available.
Regards,
Sachin