Dears,

Firstly, thank you very much for spending time reading and answering my question.

I'm about to using CM21 to level capacity for a work center, however, I have a small question about the way it works. I will explain my case by an example:

There is 3 production orders that I want to dispatch by entering a specific date entry:

My purpose:

production order A, B, and C start on 13/7 for example, then I entry date "07/08/2017" for 3 orders above.

SAP gave me:

Order A: start on 07/08/2017

Order B: Start on 08/08/2017

Order C: Start on 09/08/2017

My question is: how can I dispatch those 3 orders to a same date: 07/08/2017?

Much appreciated and looking forward for your advice.

Thanks and Best Regard,

Van Nguyen

10 |10000 characters needed characters left characters exceeded