view of lead time of product in APO

In R/3 under transaction C203 we view the time required for different operations to manufacture a product.

Where in APO does the inidividual operations time appear in APO. Specially the leadtime.

Regards,

Chetan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 21, 2007 at 10:25 AM

    Dear Chetan,

    Transaction - /SAPAPO/MAT1 (Location Product) under procurement tab

    Transaction - /SAPAPO/TL1 (TLane) Lead Time between source and destination locations

    Regards,

    Naveen.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      That should be in the PPM or PDS depending on what you have transferred to APO

      Check the masterdata sub tree in the SAP Easy access menu and you will be able to locate the Display PPM and Display PDS transactions. Load the relevant data and you will be able to locate the operation time

  • avatar image
    Former Member
    Jul 21, 2007 at 10:15 AM

    Hi Chetan,

    You can view the lead time or Planned Delivery Time in the transaction /SAPAPO/MAT1 (product master) under the tab Procurement.

    Thanks,

    Siva.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Siva,

      Thanks for your reply. but that data is maintained in R/3 Material master in MRP2 view.

      my question is related to production lead time maintained in transation C202 in R/3

      Regards,

      Chetan