How to change an existing counter reading in SAP PM?

Jul 31, 2017 at 05:14 AM

36

avatar image
Former Member

Hello Folks,

So we have got a request from Business to change an existing measurement point (which is a counter) reading to a new value. Please suggest how we can do this.

Regards,

Nihal Nayak.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Maria Terence Jul 31, 2017 at 05:24 AM
0

Hi Nihal,

First find out the measurement document you want to change and You need to reverse the measurement document and enter a new document Ik12

Measurement document - Reversal Indicator set.

In case if you want to reverse the reading before Last Measurement Reading, then you need to reverse reading for all and post it again with correct value.

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hello Maria,

Thanks for the answer. This method works, however we have to create an entirely new measuring document.

Is it possible in any way to have the same document number and merely change the counter reading?

Regards,

N. Nayak

0

I dont think its possible, even though you reverse the document. Only the reading is reversed, the document will exist in the system