on 07-20-2007 10:50 AM
I am parametrizing work schedule:
1.- I have a
daily work schedule
"V001" that has 3 different periods because the shedule is different.Period work schedule
"V01", it has only one week.Work Schedule Rules and Work Schedules
, the question is:¿Should i create so many periods in "Work Schedule Rules and Work Schedules" like "daily work schedules"?
Thanks,
Itziar Gutierrez
Hi Itziar,
In Your case you should generate Three Work schedule rules as per your Daily Work Schedules.
Regards
Pavani