on 07-28-2017 4:22 AM
Currently there are 2 process chains.
The 1st one should be scheduled on the penultimate work day of the month.
The 2nd one should run each weekend except between the penultimate work day of the month and the 5th working day of the month.
so we could either create a calendar for 1st process chain, need help to find a logic for 2nd process chain.
Hi,
you can have a look at this
https://blogs.sap.com/2014/01/17/schedule-a-process-chain-on-specific-weekdays/
grtz
Koen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can achieve this with the help of ABAPer and follow the below thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.