Hello,

Kinldy let me know how to delete a previosuly marked cost estimate , i am re running the costing run but it's failin at costing point sayin it;s already marked but we did never released it first time.

plese let me know,

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member188826
Active Contributor
0 Kudos

You have to use the Re-organization through CKR1. But be cautious of this transaction if you are using in production. If you forget to do a proper selection, you may have to repent, as it may wipe out the whole cost estimates that supports the already released cost .

Be patient and restrict as much in selection Choose the material, plant and select future cost estimate.

former_member601419
Active Contributor
0 Kudos

use CKr1