Respected Members,
i m discussing a real time issue ,kindly help me if anybody know something.
I have one subcontracting po for example in which one main item and one component is availbale.
For ex Main item : Assembly
component name: Test1
subcontracting po number :12345
and Order quantity for component in subcontracting po is :60 kg
Now for this component company has a stock of 100kg.
Suppose we are sending this component to vendor through tcode 'MB1B' with ref to po number
As soon as we give po number 12345 in mb1b automatically this component with quantity 60 kg comes ,now suppose out of 60 kg we had given only 30 kg to vendor.
So the company stock has been reduced from 100 kg to 70 kg and the still po quantity that we have to deliver to vendor is 30 kg only.
Now issue arises from here that is again if we go to second time to MB1B tcode and give the same po number 12345 ,it will be taking again 60 kg will appear automatically in the quantity and somebody can post it easily ,it won't give any warning or error message but our requirement it should not allowed more than 30 kg to post becoz 30 kg is only remaining to give that vendor.
So think is that i want to quantity to verified according to subcontracting po that once it delivered through mb1b and same po if somebody is deliverying again through mb1b then it should take the remaing quantity not more than that .
Please give me the solution.
I don't whether it can be possible through configuration setting or through abap coding.
Please whoever can help something will be appreciable.
Thanks a lot
Reply immediately.