Schedule Agreements with JIT/FRC

Former Member
0 Kudos

We are using schedule agreements with JIT and FRC. When MRP runs it generates the delivery schedule lines with the delivery dates which appear on the JIT/FRC schedule. However, when MRP pulls in the date and suggests a new (earlier date) in MD04 under rescheduling date, the date on the delivery schedule and the JIT schedule do not reflect this rescheduled date. Is there a setting or some configuration I have missed. I need to have the delivery schedule and JIT schedule reflect the rescheduled MRP dates.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you Ramakrishna,

I tried entering the data as you specified (below), but it still did not bring the rescheduled dates into the delivery schedule. I tried increasing the days and %, still no change. My rescheduled dates go back to March 07, but the delivery date still says 8/07.

A few questions:

In the Tol. profile under Legnth in workdays, what does this mean if I enter 10. Does it only check the previous 10 days? and what does each period do? Do I need to specify days and %'s in each period?

<b>Tolerance Profile</b>

You specify 10 days as the checking period for JIT schedules, since this corresponds to the release horizon. You enter 5% as upper and lower tolerance limits and choose Overall check.

Regards,

Elizabeth

Former Member
0 Kudos

I found that my issue is related to not having an MRP created with the setting to allow a start date in the past. Once I created this MRP group and added it to the material master, I can now see requirements in the past.

Former Member
0 Kudos

Hi

Changes to the overall delivery schedule in the system also lead to the creation of new JIT schedules, if these changes are not minor in comparison with the previous JIT schedule and exceed certain tolerances.

So you have to define the tolerence profile in creation of Release creation profile.

<b>Tolerance Profile</b>

You specify 10 days as the checking period for JIT schedules, since this corresponds to the release horizon. You enter 5% as upper and lower tolerance limits and choose Overall check.

Regards

Ramakrishna