Hi,
I am currently working on a project involving an upgrade from SAP 4.5B to mySAP 2005.
This is applicable to the Quality Management module.
Here is our situation:
We deal with partial lots / inspection points.
Whenever we record results for each partial lot and valuate, a follow up action is supposed to execute.
The Partial Lot Pop up box appears as expected from SAP standard functionality (During results recording in QE51N) and the partial lot valuation shows as well as the follow up action that is supposed to execute.
But the follow up action is not executing for the partial lots.
We also have another follow up action that executes after a Usage Decision is made on the overall Inspection Lot and that executes.
So i'm not sure if it a mySAP issue.
We performed this testing using the QE51N transaction.
We used QE51, and the partial lot follow up actions are executing so not sure what is happening in QE51N.