on 07-18-2007 2:20 PM
Hello,
we have SUS, SRM and R3 production system. My question is related to invoicing.
when I create an invoice through SUS, then SRM and R3 get updated in the document history with correct the Qty. However, if I create an Invoice directly in R3 with respect to the same PO, SRM gets updated but SUS does not get updated. This causes vendors to have the capability to enter more invoices than required by the PO.
Thanks
Dan
Hi
Please specify the SRM version details.
<b>Meanwhile, go through the following SAP OSS Note -></b>
<u>Note 543544 - SUS: Extended Classic Scenario for EBP not supported</u>
EBP Extended Classic Scenario (ECS) not released for SUS:
The scenario is limited for document types Purchase Order, Purchase Order Response and Change Order. But, the use of Confirmations and Invoices is not possible.
If ECS is activated in EBP and you send a purchase order from EBP to SUS you can not send the confirmation and invoice with reference to this purchase order back to EBP.
Hope this will help. Do let me know.
Regards
- Atul