hi gurus
A user tried to open a PR (EUR 21,970) on WBS element YEM-CM-PAL-NCS-NCS-NCS, and the system gave her a budget exceeded message. I checked the budget on CJ30, and it looks fine.
what could be the problem . please give me the suggestion
regards
subbu.
You can set the activity to 'warning' in Customizing temporarily, if it relates to AUC
Refer to note155823.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In addition to what subbu has said, please check following.
Go to Path
SPRO-Project Systems-Cost-Budget-Define Tolerance Limits
Under Usage column, check how much is the percentage maintained.
When your PR amount reaches that percentage of total amount, system will give message.
Hope this helps.
Regards
Tushar
P.S. Reward points for useful answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Execute the t.code: CJBN .... For the relevant project. Then system will adjust if there is any inconsistance.
all the best
Prasad.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.