hi expert,

I'm work as BI 7.0. I want to make planning application (BI-IP), my aggregration level have 3 chars : 0VERSION , 0CALMONTH, 0ORGUNIT and Key Figure :revenue. I can make planning (manually) with many version or month , ORGUNIT in the same time. I create one planning function call "copy function" to copy data from old version to new version. When I execute the copy function, it locks all records in cube (lock table show: 1KFNAME revenue [] ), this make I can't make another plan with different version or month, Orgunit in the same time . I want when I execute copy function it only lock records relevant to version , month ,org I want to copy so I can make another planning same time. Any one! pls help me.