Hi Team,
Like the Business Functions LOG_EAM_CI6 & LOG_EAM_VE_INT available now to attach DMS document to PM Order & Task List, is there any Business Function available to attach the documents to PM Measuring Document? Or any other alternate functionality available to make this happen?
I have the specific requirement to attach DMS document to PM Measuring Document.
We are in “EHP7 FOR SAP ERP 6.0” & only Object links to Measuring Point is available in standard delivery. Please assist, thanks.
Hi Yogesh,
There is a functionality available to attach to measuring point i don't think there is one available for measurement document.
You can select measuring point as an object link when you create a document in DMS using CV01N t-code.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.