Material group in purchase order can be changed even if follow-on documents are created

Jul 25, 2017 at 09:03 AM

46

avatar image
Former Member

In ME22N the material group can be changed even if the GR is done and an invoice is posted. I can't change the field selection key so that the field can't be changed in ME22N because the order is only set on hold the material group often needs to be changed. What can I do to make this field not editable anymore if follow-on documents are created?

We don't create orders with material master, only text orders.

Thank you

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Jul 28, 2017 at 07:21 AM
0

if SAP has nothing in standard then you have to do your validations in BAdI ME_PROCESS_PO_CUST