on 07-21-2017 11:25 AM
Dear Experts
When I create a Work Order (IW31) and and assign some operations in Operation Tab, then in the External tab, the Operation Quantity gets updated automatically as 1. I want to know, from where it is updating? Please refer to the screenshot.
Is this causing an issue?
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pete
I am Uploading all the Open PM orders to a new system through a Program. I have given all the required field which needs to be uploaded, but the program is giving an error- "Enter the Operation Qunatity". I thought it would update automatically but ultimately I had to include that field in the Program as well. After that it is working.
Hi Shiv,
It gets updated automatically, i dont think there is any configuration available for the same, it should be based on the SAP Standard Coding.
I have gone through SAP notes, nothing explains on the same, only SAP can provide you detailed information.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot 🙂