on 07-11-2007 5:52 PM
We are trying to identify where to establisth multiple costing lot sizes "in general" --- and in relation to use of "Variant Configuration" in regards to Costing Variants for use of the Varient Configurator.
There will be multiple Costing Lot Sizes used for 1 material. So the Material Master would not be effective. There should be something related to Costing Variants that can be assocated with Various Lot Sizes, I think?
Yes, you could use different adhoc cost estimates with varying costing lot size. If costing lot size is not mentioned when running cost estimates, the lot size is picked up from material master.