Operation split for Plant Mainteance order

Dear Expert..

I have problem in plant maintenance orders.

i want to split the orders operation daily basis without change in Work center master data.

Eg. :- i have 80 Man Hrs.(1 person) operation for the particular orders and i am utilizing the per day 08 Hrs. how can split the operation for 10 dyas.

my schedule is 10 days.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 03, 2017 at 09:07 AM

    Hi,

    If in the work center operating time 8 Hrs is maintained, by scheduling automatically schedule start and finish date will get calculated for 10 days. example Scheduling start date is 01.08.2017 Scheduling end date is 10.08.2017.

    As you mention split of operation , what I understand is split ten different operations for each 8 hours, so you need 10 operation each for 8 hours. if that is the case, you need to duplicate the operation 10 times and assign relation between the 10 operations, so the date will get changed to 10 different days. example First operation is 01.08.2017 second operation is 02.08.2017 Third operation 03.08.2017 and so on till 10.08.2017.