on 07-21-2017 6:14 PM
Hi experts,
In the transaction MM02 in the folder MRP2 we have populated the Scheduling Margin Key for Floats = 002, but when we create a production order this order does not take the Sched Margin Key 002, the production order is created with Sched Margin Key 000
Question1: Why the production orden is not created with the Sched Margin Key 002?
When in the production version we populate the MRP Distribution Key = GLEI the production order take the Sched Margin Key 002
Question 2: Why the production order take the Sched Margin Key 002 when we use the GLEI?
Best regards,
Arnulfo Cordero Pradel