cancel
Showing results for 
Search instead for 
Did you mean: 

Production Scheduler

Former Member
0 Kudos

Hi,

I would like to know the Significance of the field"Production Scheduler"which we specify in the Work Scheduling view.

Where it can be used ?

What kind of Standard reports can be obtained by using this field ?

How to make use of this in case of Repetitive manufacturing Scenario ?

kindly treat this as urgent,

regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Production scheduler is a person who is responsible for the scheduling.

You can assign scheduling profile to production scheduler & the assign in work scheduling. So that system will read the setting from scheduling profile.

If assigned directly scheduling profile in work scheduling sysyem will give priority to it, rather that scheduler.

Regards,

Suhas

Former Member
0 Kudos

Sandeep,

Prod scheduler is only for identifying the materials for which a person is responsible. Also it is possible to assign the material a prod scueduling profile through the scheduler. The same is available irrespective of discrete or rep manf.

Ram