Materials with Planning Type ND

Hi all,

For materials that are marked with planning type ND, while running MPS/MRP, there are planned orders created for the requirements created thru a Sales Order. On further investigation we found that the Item Category in the sales order item TAN has been assigned to planning types CP in our system in configuration settings VOV5 & VOV6.

What is the relation between these two and what is the basic settings in a standard SAP system for a material marked as ND?Which materials are usually marked for this planning type in a Plant?

Thanks and Regards in advance,

Deepak Prasanna S

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Jul 11, 2007 at 04:19 AM

    Dear Mr.Prasanna,

    Planning type ND will generally be assigned to consumables material type.

    Like some solutions of liquid type,beakers,test tubes etc.

    For these materials Purchase requsitions will be created manually when needed and then processed.

    For ND materials mostly costing view will not be maintained.Accounting view is sufficient for this.

    I hope this will help u in understanding it clearly.

    If useful reward points.

    Thanks & Regards

    Mangal

    Message was edited by:

    Mangal

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Deepak,

      There are lot of materials which are with MRP type ND. These are materials generally sales parts which will be procured from known vendor...these will not be manufacture...only procure and sales like in warehouse.Hence not requires any planning. for example Distributor for CAR ...he only purchase car from companies and sales as per the customer requireements.

      As i said there will be no planning reuqires...you have to create sales orders manually with no planning indicator and you can do the deleivery..Goods issues all those functions. In the sameway you have to procure with creating PO manually.

      If you ahve any question then please revert, or close this thread with suitable points.

      Regards

      TAJUDDIN

  • author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 05:40 AM

    Deepak,

    Actually the combination of MRP type and item category determines whether the requirements are passed to MRP. In standard SAP there are no requirements passed for ND.

    The item catagory is determined in sales order processing (depending on the sales configuration). Now the key which is the combination of MRP type and Item categiry determines the sch line catgory which passes the requirements to MRP.

    Hope this is clear.

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 03:50 AM

    Deepak,

    ND should not be configured for planning in VOV5 in std system. If planning is not required for a material then an MRP view will not be required hence planning will not take place. But if a material has an MRP view with PD and later you do not want it to be planned then you set it as ND. Other scenario is when you create the MRP views for all the materials uniformly but do not want to consider some materials for planning.

    Regards

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 10:55 AM

    Will ND marked materials never be considered for MRP in a standard system?

    YES, IF IT IS MARKED WITH ND, IT IS NOT PLANNED FOR THE PLANNING AND IT IS CONSUMABLE MATERIALS ONLY

    How is the link between MRP type and Item Category in a Sales Order established?

    MRP IS FOR THE PLANNING AND ITEM CATEGORY IS THE PRICE RELATED ONE IN SD

    NO LINK B/W THEM

    How this Schedule Line Category in sales order influences the requirements passing to the MRP?which setting is at a higher level..MRP type or Schedule Line Category&Item Category??

    Proposed schedule line category

    The schedule line category that the system proposes for a particular combination of

    Item category

    MRP type

    during sales order processing.

    Use

    During processing, the system automatically proposes an item category, depending on factors such as the

    Sales document type and

    Item category group

    The MRP type comes from the material master record. The resulting schedule line category determines, for example, whether the system

    Passes on requirements to MRP, and if so, what kind

    Allows goods issue

    Allows inventory management

    You can also define alternative schedule line categories.

    thank u all once again!!!

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.