Hi,

when i am trying to upload demand it gives me error as" requirement block". Can any one let me know why this error comes and can we remove them?. We upload the demnad through a z programme.It is interface programme.

Regards,

Suman

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 07:31 AM
    14

    Hi Suman,

    since this is Z program...you have to take ABAP help..i dont think we can assist you even with error message number because the class will be 00.

    I would like to know where are you uploading this demand...in MD61 or in SOP MC87. What is the errro message number and class?

    Check the staretegy in MRP4 view and this should match with the requirement types input in MD61.

    Let me know after this check.

    Regards

    TAJUDDIN

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 01:55 AM

    Hi,

    check whether you have maintained correct reqmt type

    during PIR Creation.

    check the strategy group in material master and the reqmts type in the reqmts parameters .

    Regards,

    nandha

    Add a comment
    10|10000 characters needed characters exceeded

    • You need to analyse the error step by step

      1. check if you are able to manually create the material in the md61

      2. If yes then go to 5 else continue with 3

      3. Check what is the error -

      3.A. The error will be due to incorrect or no strategygroup

      3.B. It can be due to incorrect material status

      4. If so then correct the error and then try to maually create and check it-

      5. What is the type of zprogram is it a Bdc -recording or function module.

      6. in any of the above case are u trying to do one by one period which means the report is passing single entry for each materil/plant /period combination

      7. If yes then it is a timing issue - just add a statement called "wait" in the program which your abaper knows..

      8. the timing issue means in the background for one material before the program completes the transaction the next values is populated -which may be erroring out..

      If you check all of them and your problem gets solved then just give me the feedback.

      If it didnt get solved ..just post the details of the error we will analyse it ...

      Thanks and regards

      Dskumar...

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.