Project Closure

I am trying to close the project but, The system states there is a still a PO commitment.

The original invoice allocated did not follow the prescribed % split. AP re-opened, re assigned the costs per the % split and then re-closed. PO is all in balance.

I checked the following

1. Commitment is zero for the project

2. for PO delivery and invoice is checked in. how to resolve the error

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 23, 2017 at 07:01 AM

    Hi Manju,

    Is the Final Issue Indicators are set ?

    I remember we have couple of notes for these open commitment issues, may be check the OSS

    2456540 - CJ02 WBS element with commitment can be closed

    Regards

    Terence