Hi PP Experts,

When i created a product cost collector, the cost estimate only considered the cost of materials, but has not considered activity cost like setup,production and teardown time.

How do i bring the activity cost in product cost collector?

Any suggestions will be rewarded.

Regards

Vinod

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 10, 2007 at 10:52 AM

    Vinod,

    Yes you have to give activity type in work center. This activity has to be assigned a price in KP26 for the cost center.

    Regards

    ram

    Message was edited by:

    Ramanujan Chitrakootam

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 10, 2007 at 10:41 AM

    Hi ,

    I hope you must have created a product cost collector for your HALB or FERT material using a valid production version.

    Please check whether you have mentioned some standard time for your operation or setup or labour time in the routing for each operation.

    It's assumed that for your work centre you have allocated some cost centre and also check the valid from date in the costing tab page for work centre.

    Also please check the key date of your routing.

    Please revert to the forum after checking this.

    Thanks & Regards

    Mangal

    Message was edited by:

    Mangal

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello Dear,

      Could you please tell me wherfrm did u come to know that in REM no activity types are required for work centers.

      Please include the activity type for your work centre.and its own valid cost centre.

      It means for that particular cost center you have toassign some activity type.

      In KP26,for a cost center activity type & rate is assigned.

      You have to assign the same cost centre ans activity type here.

      But As you are saying there r no activity types for ur work centre,how did u enter the time required for each operation?

      Please check ,modify and work

      Thanks & Regards

      Mangal

  • author's profile photo Former Member
    Former Member
    Posted on Jul 10, 2007 at 10:58 AM

    How do i bring the activity cost in product cost collector?

    for that go the t.code OPN2

    PLS READOUT

    Valuation variants

    A valuation variant is a parameter in a costing variant and controls the following:

    Which material prices or activity prices are used to valuate materials, internal activities, and external activities in preliminary costing

    Which material prices or activity prices are used to valuate materials, internal activities, and external activities in the actual data

    Which costing sheet is used to apply the overhead

    IN T.CODE OPN2 >>CLICK NEW AND ENTER THE VALVES THAT INDIRECTLY CONNECT TO THE PRODUCT COST COLLECTOR

    SO UNDER THIS T.CODE YOU CAN GIVE THE VALUES OF THE MATRL VALUE IF PROCURE, ACTIVITY VALVE ,SUBCONTRACT VALVE

    PLS GO THROU THE ABOVE IT WILL HELPFULL

    MAKE REVERTS

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 10, 2007 at 11:07 AM

    Vinod,

    In KKF6N just click the calculator box button once again.

    Regards

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 11, 2007 at 07:20 AM

    Vinod,

    Could you brief the forum which resolution you used to solve the problem eventually. This would help all.

    Regards

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.