Skip to Content

LIGHT OPTIMIZE ERROR - CANNOT SWITCH TO PLAN MODE

BPC 10.1 NW

CPMBPC 810 SP10

BW 7.4 SP15

hello,

when i run light optimize its failing and below is the error i see in process chain, Any idea how to fix this error? when i also try to manually switch cube to planning mode still throws the same error.

Process Switch Realtime InfoCube to Plan Mode, variant BPC: Switch cube to plan mode has status Ended with errors (instance DP8W2DW8UEOQJ4ZEG98607QOP)


Request APO_RDP8U6J8TJWFPBFBFWXKE9FEHK(0000707534) is yellow or red in InfoCube /CPMB/DNITPPT; cannot switch to planning [RSM068]


thanks in advance


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 22, 2017 at 03:59 AM

    deleted the request with yellow status in the cube & that fixed the probeln

    Add comment
    10|10000 characters needed characters exceeded