Hi All,
When I try to Schedule the Planned order it is showing the time difference between Start and End time for Planned Order as 11 seconds. The duration mentioned in the routing is 7 seconds. All the floats have been set as zero. Please can anyone tell me what other parameters the planned order looks at while scheduling. Why is there a different in time shown in Planned Order and that maintained in routing.
Some additional information:
Routing has base quantity of 3000 EA and machine time as 6 hours.
Schedule margin key = 000 i.e all the float values is zero
In-house processing time in material master is 1 day
We are not using capacity planning
Values maintained in Work Center - Capacity view:
Start 07:00:00
Finish 16:30:00 Capacity utilization 75
Length of breaks 01:30:00 No. of indiv. cap. 2
Operating time 6.00 Capacity 12.00 HR
Thanks.