Skip to Content
0
Former Member
Jul 09, 2007 at 04:54 PM

Planned Order Scheduling Time

83 Views

Hi All,

When I try to Schedule the Planned order it is showing the time difference between Start and End time for Planned Order as 11 seconds. The duration mentioned in the routing is 7 seconds. All the floats have been set as zero. Please can anyone tell me what other parameters the planned order looks at while scheduling. Why is there a different in time shown in Planned Order and that maintained in routing.

Some additional information:

  • Routing has base quantity of 3000 EA and machine time as 6 hours.

  • Schedule margin key = 000 i.e all the float values is zero

  • In-house processing time in material master is 1 day

  • We are not using capacity planning

  • Values maintained in Work Center - Capacity view:

Start 07:00:00

Finish 16:30:00 Capacity utilization 75

Length of breaks 01:30:00 No. of indiv. cap. 2

Operating time 6.00 Capacity 12.00 HR

Thanks.