Total Pl. costs are different compare to table RPSCO and CN52N report.

Hi folks,

for project CP00949 activity 0120 and 0220 table RPSCO (zet003) gives 338.094 and 49.401, where as CN52N gives as total resp 337.612 and 39.118

Any kind of suggestions arr welcome and will be rewarded well.

Thanks in advance,

regards,

Harisha

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jul 10, 2007 at 04:38 AM

    Hai Harisha

    The cost which seen in Table RPSCO(zet003) and in CN41 /Cn41N (not in Cn52N)

    is not matching.

    Check in report S_ALR_8701352 which gives at each individual activity level and at WBS level.

    check the entries once again.

    ENJOY SAP PS