on 07-09-2007 2:22 PM
Hi folks,
for project CP00949 activity 0120 and 0220 table RPSCO (zet003) gives 338.094 and 49.401, where as CN52N gives as total resp 337.612 and 39.118
Any kind of suggestions arr welcome and will be rewarded well.
Thanks in advance,
regards,
Harisha
Hai Harisha
The cost which seen in Table RPSCO(zet003) and in CN41 /Cn41N (not in Cn52N)
is not matching.
Check in report S_ALR_8701352 which gives at each individual activity level and at WBS level.
check the entries once again.
ENJOY SAP PS