Quantity Problem

Former Member
0 Kudos

have a issue.

When I check the Operation Quantity & Base Quantity in Master recipe it is showing difference in the quantity

I want to just clarify from where does this Operation quatity comes Can u tell me the tcode. Does it pick from the routing

regards

Pushkaraj

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

hi All

Can anyone explain me the meaning of the below sentence

Denominator for the quotient that gives you the relation between the routing unit of measure and the operation unit of measure

Where it is maintained and what are the setting It is a field in Display Master Recipe Operation ( Standard Values Tabs)

Regards

Former Member
0 Kudos

This is maintain in operation detail screen. Go to routing select operation and go to opeartion details. I think this is in general data tab in recipe.

Regards

TAJUDDIN

Former Member
0 Kudos

hi All

can anyone explain me the meaning of the below sentence

Denominator for the quotient that gives you the relation between the routing unit of measure and the operation unit of measure

Where it is maintained and what are the setting It is a field in Display Master recipe Operation ( Standard Values Tabs)

Regards

Pushkaraj

Former Member
0 Kudos

Yes it is correct, But if there r several operations say for example

Oper 10,

Oper 20

Oper 30

There is varation in quantity

So how can we find it 7 where it is maintained

Regards

Pushkaraj

Former Member
0 Kudos

Hi Can u please eloborate exactly from where does the Operation quantity comes If posssible with an example

Regards

Pushkaraj

Former Member
0 Kudos

Hi,

Operation qty is your reqmt qty which comes from your demand.

Ex PIR 100PCS

MD02/MD04

Planned order will be created for 100 pcs.

convert it into Production order

Now your operation qty is 100pc.

Regards,

nandha

Former Member
0 Kudos

Hi,

Base qty - When we create a BOM for a finish material the qty is 1, which we set in customisation. Create BOM by considering 1 qty of FG or SFG.At the time of creation you can chage the base qty.

Operation qty.- When we create PIR or sales order that qty is operation qty. When we take MRP run system read BOM & calculate qty as per BOM.

Base qty of FG is 1 & raw material is 1

If order qty is 100 then system will calculate required raw material i.e. 100.Create PR.

Regards,

Suhas

Former Member
0 Kudos

Hi,

Operation quantity is picked from the order quantity that you have keyed during order creation.

Base quantity is the quantity that you specify in the task list for defining the various time like machine, labour etc like for e.g for operation 10, the base quantity could be say 10 and w.r.t. this base quantity one will define the machine, and labour times for that operation 10. For operation 20 the base quantity could be different.

Now when you create and order, the order quantity is the operation quantity and the time required to complete that operation is calculated based on the base quantity from the task list that has being copied in the order.

I hope this resolves your query.

Thanks & Regards.

Santosh Joshi.