CKMLCP Costing run and period not belong to the company

Dear all

we have new live system ,it was copied form old production system to new one ,we was done cross client copying to other client without actual data .

Now we want to perform ckmlcp in new system ,

when i define Costing run :80001707 Period 07 2017,and plant Assigment was 8000 belong to 8000 company code .and when I Create Cost Estimate and there is an error messge

Costing run GFZ1512 post period 12 2015 was not found .

2.png (36.5 kB)
1.png (21.1 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jul 26, 2017 at 05:33 AM

    Hi Anna

    Please check whether your MM period (OMSY) and FI period (OB52) set to 07.2017.

    Bhaskar