we have new live system ,it was copied form old production system to new one ,we was done cross client copying to other client without actual data .

Now we want to perform ckmlcp in new system ,

when i define Costing run :80001707 Period 07 2017,and plant Assigment was 8000 belong to 8000 company code .and when I Create Cost Estimate and there is an error messge

Costing run GFZ1512 post period 12 2015 was not found .

2.png (36.5 kB)
1.png (21.1 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Bhaskar Basam Jul 26, 2017 at 05:33 AM
0

Hi Anna

Please check whether your MM period (OMSY) and FI period (OB52) set to 07.2017.

Bhaskar