Drag & Drop in Planning Board pp/ds

Hey experts,

I would like to drag and drop orders in PP/DS Resources Planning board but when I do, they either start at midnight or finish at midnight of the closest day (depending on the scheduling direction). The strange thing is that it only happens when i drag and drop, if i click on RESCHEDULE button i can place the order at 3pm for example. I used to be able to drag and drop normally to whatever time i chosed, i dont know what happened that changed the configuration. Scheduling mode is INIFINIT SEQUENCING and finite capacity is TIME CONTINUOUS-CAPACITY.

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 03, 2017 at 08:16 PM

    Hello Luca, hope you are fine.

    I would like to know if are you using a custom Profile, or SAP Standard profile?

    In case of custom profile, I recently had a case about almost same issue, please check KBA below:

    2496403 - Order scheduling does not respect the specific date / time

    BR,

    Yasmin Alayyan.