Former Member
Jul 28, 2017 at 11:38 AM

Drag & Drop in Planning Board pp/ds

553 Views

Hey experts,

I would like to drag and drop orders in PP/DS Resources Planning board but when I do, they either start at midnight or finish at midnight of the closest day (depending on the scheduling direction). The strange thing is that it only happens when i drag and drop, if i click on RESCHEDULE button i can place the order at 3pm for example. I used to be able to drag and drop normally to whatever time i chosed, i dont know what happened that changed the configuration. Scheduling mode is INIFINIT SEQUENCING and finite capacity is TIME CONTINUOUS-CAPACITY.

Thanks in advance.