Dear Experts,

While running CCR for manufacturing orders I get error code 173 - difference in confirmation status.

There are basically two scenarios I observed.

1. The process order is of released status (today's date) and there was a change of partial delivery happened and in APO the order is showing initial order quantity (change did not get reflected and captured in CCR) on pushing it moves to APO and showing the correct order quantity. - This part I understand.

2. The process order is of released status too but I could see two process order (with same order number) but with different date (one of Today and another of other day and the order quantity is equally distributed). But in APO I could see the whole order quantity on the second date (later date). This is getting captured in CCR with 173 error code and not getting moved to APO. - can you please help in understanding on this and help in get rid of this error code 173. Many Thanks.

Regards,

Yasar