Planning table CM25 Finite sheduling - whole shift skipped

Jul 20, 2017 at 08:01 AM


avatar image

Dear gurus,

I am facing a strange behavior of CM25 regarding shifts definition while scheduling capacity requirement..

I am using overall profiel to view work center/capacity with 2 charts. That's okay. Here is a screenshot of the strategy profile:

And here comes shifts definition:

As you can see the transaction shows shifts in the Gantt chart correctly.

BUT! When I try to drag the order to the second shift, this is gonna happen every time.

It looks like the second shift is skipped somehow. That's why the order's end is rescheduled till the next mornig shift. But why? Some inconsistency regarding capacities?

I'll be glad for any clue.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Jul 20, 2017 at 05:02 PM

Did you make sure that a reference to the version of available capacity 1 was set in the capacity header?

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Yes I did. No problem there.