Dear Experts,

While running the costing for a finished product , only the BOM is getting picked and the routing is not picked. We are using the costing variant PPC1 . Both the BOM and the Routing are released and in active status. When we ran the costing run, both BOM and routing are picked correctly. Please advice the possible reasons why the routing is not picked.

Thanks.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

shailesh mishra Jul 20, 2017 at 07:37 AM
0

hello,

please check the lot size of routing with costing lot size. Are they same or different?

Best regards

Shailesh Mishra

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks. Shailesh. Yes the costing lot size is with in the production version lot size range.

0
avatar image
Former Member Jul 20, 2017 at 05:31 AM
0

Hello ,

Check the activity type price is maintained or not.

Elliott.c

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Thanks Elliott. The activity prices are already maintained.

0
Former Member

Hello , is there any log messages in CK11N ?

0
Amit Sharma Jul 21, 2017 at 09:02 AM
0

Hi,

Are your activity prices not fetching while costing run ?

Kindly check with cost elements of activities maintained in cost component structure (OKTZ) and Prices maintained in KP26 against activity and cost center. Check costing variant

Regards,

Amit

Share