Skip to Content

Routing not picked in the Costing Run

Dear Experts,

While running the costing for a finished product , only the BOM is getting picked and the routing is not picked. We are using the costing variant PPC1 . Both the BOM and the Routing are released and in active status. When we ran the costing run, both BOM and routing are picked correctly. Please advice the possible reasons why the routing is not picked.

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jul 20, 2017 at 07:37 AM

    hello,

    please check the lot size of routing with costing lot size. Are they same or different?

    Best regards

    Shailesh Mishra

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 20, 2017 at 05:31 AM

    Hello ,

    Check the activity type price is maintained or not.

    Elliott.c

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 21, 2017 at 09:02 AM

    Hi,

    Are your activity prices not fetching while costing run ?

    Kindly check with cost elements of activities maintained in cost component structure (OKTZ) and Prices maintained in KP26 against activity and cost center. Check costing variant

    Regards,

    Amit