How to setting WBS display options in CJ40 or CJ30

Hi,

I hope default using description when I maintain cost plan in CJ40, WBS element display is description .

Thanks!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jul 04, 2007 at 04:28 AM

    Hai

    To plan / set the Cj40 or Cj30 for a WBS element - first the operative indicator of WBS - "Planning Element" should be enabled.

    ENJOY SAP PS.

    Regards

    PP

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi,

      I know you say that indicator in CJ20N, but i hope to see using description display WBS when i enter in cj40 or cj30.

      you know ,as you enter in CJ40 or Cj30,then select 'setting'----->display options -->

      using description. I hope default display using description.