cost center validity period change

Former Member
0 Kudos

Hello,

When I created a new cost center, I gave the wrong date range. I put validity period as 12/06/2007--12/31/9999

it should have been <b>07/01/2007-12/31/1999</b>

The system doesn't allow me to change the analysis period as its back dated. Any idea? Should I be blocking the cost center and creating it again with the correct date format?

Correct help gets point!!!

Thanks,

Rob

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Rob, to follow on from the other posts, the top two identify how you add a new range.

However I am guessing the problem you have is that you dont want it open until a certain date. If that is the case, you should have two date ranges, once you have created the second interval.

Make sure you block the second one.

Former Member
0 Kudos

hi rob..... is this solved....

Answers (3)

Answers (3)

Former Member
0 Kudos

goto KS04.. enter the cost center. Enter the time period for which u want to delete the cost center. enter the date upto which u wanted the end date as the start date of the deletion.... it will delete the cost center for the future time period.... this will do....

Former Member
0 Kudos

Thank Nimit!!

You got it right. Thanks everyone else for their prompt reply. I had actually already found the solution that Nimit came up with.

Former Member
0 Kudos
siva_boni
Active Participant
0 Kudos

To change the cost center validity period:

1. go to KS02, enter the cost center

2. from menu, Edit -> Analysis Period -> Other Analysis Period -> enter in the new validity period.

I hope above helps you.

Regards

Siva