Hi,

I'm working on progress for project. I have test the measurement methods.

But I want to calculate a POC for the project in global, I don't want to have just the POC for an object. Is it possible to have the POC for the intern activities, the element of WBS and the main WBS (for the project in general) ?

On Help SAP I've seen : "The system uses a suitable weighting to aggregate the POC for the activities in the WBS element. " Which element do I have to enter to obtain this result ? In the progress of a WBS, I mention which measurement methods...

I think it's important to see clearly and quickly what is the POC of the project and not only each objects.

Thanks for your help. Warm regards

Benny