Which report to run after changing number of days in OVA8

Jul 18, 2017 at 11:43 AM

33

avatar image

Hello Team

We have a requirement to change the number of days in automatic credit control settings in OVA8 transaction. After moving the changes to production client, we would like to know which report(s) we need to run in sequence if any. As of now I have found the following reports but not sure just for changing the "number of days" field do we need to run all these reports!

RVKRED77, RVKRED88, RVKRED09 and RVKRED07;

Could you please help on this?

Williams

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

G Lakshmipathi
Jul 18, 2017 at 01:26 PM
0

Had I been in your position, I would run a test scenario, do the required configuration change, run the report and see what is the outcome, so that I will come to know immediately.