Is there a way to mass convert purchase requisitions to schedule lines directly?
The material for this scenario would have a scheduling agreement and source list defined but i am unable to use ME59 to do this. All the indicators for auto PO have been checked.
Hi,
In transaction ME38, you may create delivery schedules with reference to the MRP generated PR
Regards,
Prashant Kolhatkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For creating schedule lines automatically, you have to maintain at source list the vendor & schedule agreement number & mark at MRP column as 1 (MRP relevant). Then system will generate the schedule lines from MRP
Regards,
Prashant Kolhatkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.