I could not find any way to look at BOM cost - the display BOM function does not seem to offer this feature. Access to BOM cost is necessary to the project management team and hardware design team at minimum.

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 11:18 AM

    Niraj,

    You can check while doing the costing. CK11N - costing run. CK13N - Display. Under the materials cost you can identify the BoM cost.

    Regards

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 11:22 AM

    Hi Niraj,

    Costing feature is not available in BOM menu. If you have valid BOM for the production/costing usage then you can run the costing run from CK11n and the same you can display from the CK13n transaction.

    Better you take help from costing persons in your project.

    If any questions then please inform.

    Regards

    TAJUDDIN

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 11:34 AM

    BOM for the production/costing usage,

    costing run from CK11n and display by the CK13n transaction.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2007 at 06:39 AM

    Hi Neeraj,

    The case may be 1. U r created BOM in which costing indicator is not checked in BOM i.e relevancy to costing and then you run standard cost estimete for that month i.e Ck11n and ck24 so you can not costing of that component as it is not relevency to costing.

    U have to wait for one mont of this fiscal yer ain next month you change the production verision and update the BOM in hcih costing indicator is checked

    \then run Ck11n, same u can se in display Ck13n and update the same in CK24.

    U will get the csotig of BOM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 04, 2007 at 06:43 AM

    Niraj,

    You should use transaction "CK86" or "CK86_99" to access BOM cost alone.

    Reward your points and close the thread.

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.