Is it any link between one batch to another batch since we need

> batch Wise trace out . is it any T-code is available??? ?? for example

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 08:50 AM

    Hi,

    First activate setting in OCHA, where used list. Then u can see by T code BMBC.

    Enter material, select particular batch - detail. You can see batch traceability top to bottom and also bottom to top.

    Regards.

    Suhas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 08:54 AM

    Hi Jagadesh,

    Follow this link and click on "Create a Batch Managed Material Master Record" and " Create a Batch"

    https://www.hostlogic.hu/caghelp/Navigation/1026.htm>

    Hope this will give you a complete idea.

    Regards

    Rehman

    Reward Suitable Points.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 02, 2007 at 09:32 AM

    Hi,

    You can use 'MB56' .There you can use top-down or bottom up approach.

    Regards,

    Shailendra

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      After you activate the Batch where used list in OCHA .

      You can directly run MB56.

      This MB56 is batch where used list.

      Batch traceability.

      This will be used when you have a complaint about a finished product.

      Then if you want to find out which batchecs of ROH were used in that batch of FERT . It can drill down upto Purchase deatils of ROH etc.

      Hope this answers you if you are looking for the batch traceability of FERT & ROH.

      Regards

      YMREDDY

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2007 at 06:10 AM

    HI,

    Once you activate batch management in SPRO i.e at plant level, client level and material lavel as per ur requirement.

    The best T-Code is BMBC as many suggested yhis is batch manufacturing cokpit.

    Also batch where used list, MB56, MB5C .

    U check this t code

    Regards

    Siddhesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 10, 2007 at 07:12 AM

    I have another question - the standard MB 56 where used report, is run for specific part and batch #. The report cannot be run for a specific part with all batch numbers since "*" is not accepted.

    I am looking for an option that will generate report for a specific batch having more than one materials. Would any of you be aware of it?

    Alternately is it possible to run the MB56 report where the variables - material and batch number are in a spreadsheet and the the query reads the values from the spread sheet to generate a comprehensive report?

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.