cancel
Showing results for 
Search instead for 
Did you mean: 

diffrence in daily req and indiv. req

Former Member
0 Kudos

Hi Gurus

can anybody explain me the diffrence between Daily requirements and Individual reqmt.which are used in avalabilty check in MRP3 view of material master.

thanks in advance

kk

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In scope of check checking group and checking rule are assigned,

Again checking group is assigned in MRP 3 and checking rule is assign to checking control.i.e. PP. Material is being checked as per setting in scope of check during order creation & order release. Also as per setting in checking control.

If u enter 01 system will carryout availbility of material where 01 group & checking rule is assigned in scope of check.

Regards,

Suhas

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Kedar,

If you set 01 as a daily requirement in stock requirement list (MD04) u can see the total requirement in a day.

If u set 02 as a individual requirement in stock requirement list will show the requiremnt individually.So that we can can see the requiremnt of each order seperately.

It will help u.

Regards,

Suhas

Former Member
0 Kudos

Hi,

For ex if a 2 sales order comes today for same material then in MD04 it will

be shown as cumulated qty if you set the availability check as daily reqmts.(01)

Two sales order will be shown separately if you set availabilty check as individual reqmts.(02)

Regards,

nandha

Former Member
0 Kudos

Hi nandha

but why it is in avalability check?

regards

kk

Former Member
0 Kudos

Hi,

For this check only you are linking the order type in checking control

Availability check during order creation /order release

Regards,

nandha