Hi Gurus,

Again I need your help. I want to receive a semi finished material from our vendor using sub contract PO.

Semi finished material : 30015

Raw material : A205

Purchase order is created for 30015 in ordering unit TS (thousand). We have a BOM with following relation:

1000.000 TS (100,0000 EA) of 30015 needs 80 KG (80,000G) of A205.

I have got a PO of 1000 TS and when I am receiving it I get following error:

ERROR:

Notified Qty Exceeded by 80 KG/ 80,000 G.

Can any one reply me to fix the issue.

Thanks in Advance

Shiv (my colleague Rajaram all ready logged the same issue)

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Shiv,

this means subcontractor doesn't have A025 to delivery 30015, check subcontractor stock overview in ME20 or MBLB if he has sufficient stock of A025 to convert 30015.

Regards

Former Member
0 Kudos

Hi,

Thanks,

There is a stock and being displayed in ME20 and MBLB.

Thanks

Shiv

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Shivu,

Can you tell me the what are all the steps you have done while creating a

Sub-contracting PO.